pelletizing plant progress rate reaches 55 percent

pelletizing plant progress rate reaches 55 percent

Providing its own required pellet for PASCO DRI plant and to supply in local market, PASCO (Pasargad Steel Complex) has decided to establish one 3.4 MTPY pelletizing plant based on Rotary Kiln Technol
پنجشنبه, 10 مرداد 1398

Providing its own required pellet for PASCO DRI plant and to supply in local market, PASCO (Pasargad Steel Complex) has decided to establish one 3.4 MTPY pelletizing plant based on Rotary Kiln Technology. Being capable to utilize a vast range of concentrate with different analysis and moisture content, this plant is furnished by needed requirements including Dryer, HPGR, several arranged concentrate bins and etc. After 16 months from project start, it hits 55% progress and is predicted to be finished in less than 10 months to provide required pellet of under construction DRI plant.